In what order should you renovate?

Demolition, services, plasterboard, screed, painting, floors: the standard schedule of a full renovation — and why the wood floor comes last.

Pièce en cours de rénovation avec escabeau placo et peinture

Nine failed renovations out of ten are not technical failures: they are ordering failures. The tiler comes before the electrician, the wood floor arrives before the paint, and everyone comes back twice. Here is the standard schedule that site managers follow, with durations and checkpoints before each phase.

The project timeline

1. Demolition1-2 wks2. Services2-3 wks3. Insulation + boards2-4 wks4. Screed/levelling+ drying 2-6 wks5. Painting1-2 wks6. WOOD FLOOR+ skirtings, touch-upsRealistic total for a full renovation: 3 to 5 months — substrate drying times cannot be compressed

Phase 1 — Demolition and structural work

Removing coverings, demolishing partitions, openings in load-bearing walls (with a structural engineer), replacing external joinery. Checkpoint before phase 2: watertight, airtight, wall moisture diagnosed.

Phase 2 — Services

Electrics (conduits, boxes, board — see our electrical standard guide) and plumbing (PEX, multilayer or copper) go in with the walls open. Checkpoint: 24 h documented pressure test, labelled circuits, photos of every chase BEFORE closing — they are worth gold ten years later.

Phase 3 — Insulation and partitions

Wall linings, plasterboard partitions, suspended ceilings, joint taping. Checkpoint: continuous vapour barrier, reinforcements at future fixing points, joints checked under raking light.

Phase 4 — Substrate floors

Screed or levelling compound as needed, underfloor heating where applicable. The drying times cannot be compressed: 1 week per cm of screed up to 4 cm, moisture ≤ 3 % (0.5 % anhydrite) required before the wood floor. Painting is planned during this drying.

Phase 5 — Painting and wall finishes

Primer + 2 coats before the final floor: a drop of paint wipes off a screed, not off an oiled wood floor. Keep the final touch-up for the very end.

Phase 6 — Finish floors, the wood floor last

The wood floor is the noble covering of the project: it arrives when the dust has settled, humidity stabilised, heating running. It needs 48 h of acclimatisation in the room (packs closed, flat — the protocol here), a compliant substrate, then installation — glued, floating or nailed. Then skirting boards, trimmed doors, paint touch-ups.

Budget and lead times

Order long-lead items from phase 3: joinery, kitchen… and the wood floor. Buying your flooring direct from the mill saves budget for the rest of the project — and our 7-10 day lead times fit a phase 4 finish perfectly. Use our m² calculator to order the right quantity (+ 8 to 10 % waste depending on the pattern).